Application Process Steps:

  • Contact staff and describe your project.
  • You may require additional approvals, such as a Minor Variance, By-Law Amendment, Official Plan Amendments, CRCA, SLPC or Health Unit approval
  • Once you have the information and have spoken to staff you can submit your building permit for staff to review.
  • Once you receive your building permit you can proceed with your project.

How long does it take to get a building permit?

Applications are reviewed by the Chief Building Official within 10 business days and staff will contact applicant regarding status of the permit for these types of construction:

  • a detached house, semi-detached house, townhouse, or row house where no dwelling unit it located above another dwelling unit
  • a detached structure that serves a building described in clause (a) and does not exceed 55 m2 in building area
  • a tent to which Section 3.14 of Division B of the Ontario Building Code applies
  • a sign to which Section 3.15 of Division B of the Ontario Building Code applies

Other types of construction may require additional time for review as indicated under the Ontario Building Code.

 

Site plan with a stamp saying building permit.  There is a hand holding a building permit stamper

Sign up to our eNewsfeature

Stay up to date on the Township's activities, events, programs and operations by subscribing to our eNewsfeature.